Black listing of a contractor is a weapon in the hands of the employer that can be used against a contractor for a breach of contract or any willful default to complete the project as per the contract etc.,
Most of the contracts have such provisions to avoid a defaulted contractor bidding for another work. But in some cases, employers go ahead and use it like a punishing provision even after the issues between the parties are determined by a competent judicial authority. One such case Patil Rail Infrastructure Private Limited Vs S.L.Gupta and Another (2019) SCC Online Del 6724 was recently on 25th January 2019, decided by Justice Mr Vibhu Bakhru of the Delhi High Court by beautifully written Judgment, deciding the sustainability of a notice for black listing issued after an arbitration award.
In the above said case the petitioner contractor received a show cause notice from IRCON seeking explanation from the contractor alleging various lapses on the part of the petitioner in production and supply of Railway sleepers at its plant at Thirumangalam, Tamil Nadu. The petitioner was the contractor for supply of Railway Sleepers to Indian Railway through IRCON. The Petitioner contended that the impugned notice is wholly unsustainable in law since all disputes stands concluded by way of an arbitral award passed in favour of the petitioner. The Petitioner further contended that it is no longer open for IRCON to raise these issues again and initiate action of black listing against the Petitioner. The Respondent contended that the quality issues raised in the show-cause letter do not include the issues determined in the arbitration proceedings and hence IRCON is not precluded from taking action against the contractor.
The petitioner was the contractor for the manufacture, supply and transportation and delivery of Pre-Stressed Mono block concrete Sleepers (laying) track and special concrete sleepers for laying down Broad Gauge Railway track as per Indian Railway Specifications for the contracts of restoration of various railway lines in northern Province of Sri Lanka. On 17.06.2013 IRCON wrote a letter to the Petitioner stating that the railway sleepers supplied by the petitioner had developed cracks and demanded replacement of those sleepers. The petitioner contended that the material was supplied only after inspection and hence petitioner cannot be made responsible for the same. Arbitration was initiated by parties. Joint tests were conducted by the experts at IIT (Indian Institute of technology), Chennai. IIT certified that the said sleepers did not fail any test relating to any parameter and the report regarding the same was submitted to the Arbitral tribunal. Hence arbitral tribunal passed an award in favour of the petitioner holding that the petitioner was not responsible for the cracks that had developed in certain sleepers. The Application filed by IRCON under S.34 was also dismissed.
Delhi high court examined the contentions of parties and found that the issues raised in the show cause notice were also raised in the arbitration proceedings and were determined by the Arbitral tribunal. Hence, the Court set aside the impugned notice stating that it is not open to IRCON to raise the same issues that were concluded in the Arbitration proceedings by way of a proceeding to black list the petitioner.
Ineligible Arbitrator can be challenged even in Pre- 2015 cases and at any point of time
Supreme Court of India in its recent Judgment dated 04th January 2022 pronounced by the bench consisting of Hon’ble Justices Mr M.R.Shah and Mrs Nagarathna in the case of Ellora Paper Mills held that the mandate of the arbitrator can be challenged at any point of time during the proceedings, in view of Section 12(5) read with Seventh Schedule of the 1996 Act.The Impact of Limitation Act on MSMED Act Recovery Proceedings
In the realm of commercial disputes, the intersection of the Limitation Act, 1963, and the Micro, Small and Medium Enterprises Development (MSMED) Act, 2006, has been a subject of legal scrutiny. A landmark judgment by India's Supreme Court in the case of M/s Silpi Industries vs. Kerala State Road Transport Corporation & Anr has shed light on whether the time constraints of the Limitation Act apply to arbitration proceedings under Section 18(3) of the MSMED Act. This decision has significant implications for businesses within the MSME sector, which is a powerhouse of economic growth and innovation in India.SUPREME COURT OF INDIA RECOGNISES ENFORCEMENT OF EMERGENCY ARBITRATOR AWARD
Prior to 2010, if a party to an international arbitration requires to get an interim order, prior to formation of the arbitral tribunal, it was left with no other option other than approaching the appropriate National Court of the Respondent or the National Court having the jurisdiction over the subject matter covered under the application for interim order.